A- Red Category

The Inspection Team usually comprises of one or more officers, as the case may be, to carry out inspections under the provisions of various environmental legislations.

  • A notice is served by the Inspection Team to the occupier or Authorized /responsible person in case of samples to be collected u/s 21 of Water (Prevention & Control of Pollution) Act, 1974 and u/s 26 of Air (Prevention & Control of Pollution) Act, 1981.
  • The Team shall verify the following, in the presence of the occupier or authorized/responsible person:-
    • Operation of plant(s), product(s) being manufactured, raw material being used with quantity,
    • Status of operation of Environment Management System comprising of generation and Control measures taken for Water I Air /Solid Wastes/Hazardous Wastes and their storage and disposal.
    • Maintenance of records in the form of logbooks etc. for pollution control devices, energy meter reading, raw consumption of water/fuel and other as required by the Inspection Team.
    • Number of outlets provided for disposal of waste water/liquid waste and compliance thereof.
    • Number of emission stacks/vents /boilers/ furnaces with their capacity etc.
    • Area within or outside the premises to check any unauthorized disposal or general housekeeping.
    • The compliance of the conditions of previously granted Consents / Authorizations under Environmental Laws.
    • Online Continuous Monitoring system details (if applicable)
    • CCTV Cameras (if applicable)
  • The Team shall also collect sample(s) of waste water, emission(s) and hazardous waste(s), as required by the Team.
  • The Inspection Team while conducting inspection, serves the notice to take the samples of effluent or emissions, giving brief remarks on the notice, regarding shortcoming found, if any.
  • Checklist of documents that may be verified by the Inspection Team during its visit are as follows:
    • Production details
    • Raw Material details
    • Water / Fuel Consumption Data
    • Solid Wastes /Hazardous Waste Generation and Disposal Records and Logbooks
    • Electricity readings and logbooks regarding consumption of electricity for running the Pollution Control Devices.
    • Compliance of any other direction given by SPCB/CPCB/MoEF &CC or any other court of Law

B- Amber/Orange Category

The Inspection Team usually comprises of one or more officers, as the case may be, to carry out inspections under the provisions of various environmental legislations.

  • A notice is served by the Inspection Team to the occupier or Authorized /responsible person in case of samples to be collected u/s 21 of Water (Prevention & Control of Pollution) Act, 1974 and u/s 26 of Air (Prevention & Control of Pollution) Act, 1981.
  • The Team shall verify the following, in the presence of the occupier or authorized I responsible person:-
    • Operation of plant(s), product(s) being manufactured, raw material being used with quantity,
    • Status of operation of Environment Management System comprising of generation and control measures taken for Water /Air /Solid Wastes/ Hazardous Wastes and their storage and disposal.
    • Maintenance of records in the fonn of logbooks etc. for pollution control devices, energy meter reading raw consumption of water/fuel and other as required by the Inspection Team.
    • Number of outlets provided for disposal of waste water/liquid waste and compliance thereof.
    • Number of emission stacks I vents I boilers/ furnaces with their capacity etc.
    • Area within or outside the premises to check any unauthorized disposal or general housekeeping.
    • The compliance of the conditions of previously granted Consents I Authorizations under Environmental Laws.
  • The Team shall also collect sample(s) of waste water, emission(s) and hazardous waste(s), as required by the Team.
  • The Inspection Team while conducting inspection, serves the notice to take the samples of effluent or emissions, giving brief remarks on the notice, regarding shortcoming found, if any.
  • Checklist of documents that may be verified by the Inspection Team during its visit are as follows:
    • Production details
    • Raw Material details
    • Water/Fuel Consumption Data
    • Solid Wastes / Hazardous Waste Generation and Disposal Records and Logbooks
    • Electricity readings and logbooks regarding consumption of electricity for running the Pollution Control Devices.
    • Compliance of any other direction given by SPCB/CPCB/MoEF &CC or any other court of Law.

C- Green Category

The Inspection Team usually comprises of one or more officers, as the case may be, to carry out inspections under tile provisions of various environmental legislations.

  • A notice is served by the Inspection Team to the occupier or Authorized /responsible person in case of samples to be collected u/s 21 of Water (Prevention & Control of Pollution) Act, 1974 and u/s 26 of Air (Prevention & Control of Pollution) Act, 1981 .
  • The Team shall verify the following, in the presence of the occupier or authorized / responsible person:
    • Operation of plant(s), product(s) being manufactured, raw material being used with quantity,
    • Status of operation of Environment Management System comprising of generation and control measures taken for Water /Air /Solid Wastes/ Hazardous Wastes and their storage and disposal.
    • Maintenance of records in the form of logbooks etc. for pollution control devices, energy meter reading raw consumption of water/fuel and other as required by the Inspection Team.
    • Number of outlets provided for disposal of waste water/liquid waste and compliance thereof.
    • Number of emission stacks I vents I boilers/ furnaces with their capacity etc.
    • Area within or outside the premises to check any unauthorized disposal or general housekeeping.
    • The compliance of the conditions of previously granted Consents I Authorizations under Environmental Laws.
    •  
  • The Team shall also collect sample(s) of waste water, emission(s) and hazardous waste(s), as required by the Team.
  • The Inspection Team while conducting inspection, serves the notice to take the samples of effluent or emissions, giving brief remarks on the notice, regarding shortcoming found, if any.
  • Checklist of documents that may be verified by the Inspection Team during its visit are as follows:
    • i. Production details
    • Raw Material details
    • Water / Fuel Consumption Data
    • Solid Wastes / Hazardous Waste Generation and Disposal Records and Logbooks
    • Electricity readings and logbooks regarding consumption of electricity for running the Pollution Control Devices.
    • Compliance of any other direction given by SPCB/ CPCB/ MoEF &CC or any other court of Law